Guides / DLP 1-year re-check before it ends

HDB defects liability period (DLP): how to do your month-11 re-check before it ends

Updated 2026-09-30

Your first defect check happens at key collection, but some problems only appear after months of daily use, rain and aircon. HDB gives new flats a 1-year defects liability period (DLP) from the date you collect your keys. A second, shorter check around month 10 or 11 is how you make sure nothing slips past it.

What the DLP is, in plain terms

HDB also asks owners to report defects within one month of key collection and before renovation starts. That avoids arguments later about whether a problem came from construction or from renovation works. The month-11 re-check doesn't replace that first check; it catches what has developed since.

When to do the re-check

Aim for month 10 or early month 11. That leaves time to report, wait for the joint inspection, get the repair done and check it before the year runs out. If you're still renovating or haven't moved in, do it anyway: an empty flat is easier to inspect.

What to re-check, room by room

Walls and ceilings

Floors and tiles

Bathrooms and kitchen

Windows and doors

Electrical and fittings

How to report it so it gets fixed

  1. Tape and number each defect, for example #12, the same way you did at key collection.
  2. Take two photos per defect: a close-up showing the tape, and a wider shot showing where it is in the room.
  3. Write the exact location, such as "Common bathroom, ceiling above shower, near vent".
  4. Submit before the DLP ends, online or at the BSC, and keep a copy of what you submitted and the date.
  5. Attend the joint inspection with your list and photos, and check each repair at the closing inspection.

A note on renovation

If your contractor has hacked, drilled or waterproofed an area, a defect there may be treated as renovation-related rather than a construction defect. That's why the photos and report from key collection matter: they show what the flat looked like before work began. Keep them with your re-check photos so you can compare the same spots.

Quick month-11 checklist

Do the whole check on your phoneKeyDay walks you room by room, numbers each defect to match your tape, and builds a PDF report with photos and a labelled floor plan for your BSC or contractor. Free to try; S$19 one-time for the full version.Try KeyDay free